The primary client concerns included:
Continuous access during the milling, repaving and striping operations
Cost
Schedule and time management
Quality surface at the project’s end
After reviewing the jobsite in person, we came up with a range of possible solutions that would meet the client’s needs.
Milling and grading operations
Tearout and rebuilding of existing valley gutter
Due to sub-grade issues. We proposed milling the existing pavement down 2” from the existing surface and laying approximately 2,500 tons of ½” aggregate hot mix, in addition to the replacement of 1,500 linear feet or 90 cubic yards of concrete valley gutter. Our recommendations and proposed fix were accepted by Calvac’s client and HOA Board. The job was undertaken in phases as to not disrupt the community at one time.
The end result of the San Harbour South HOA project looked fantastic! The project went off without any difficulty and was completed within the stated schedule and budget.
Calvac Paving is proud to have served the Bay Area for over 45 years with a wide range of paving, concrete and ADA access planning and implementation solutions. Why gamble with the outcome of your project? Make sure your contractor can get it done right the first time, every time. To learn more about how Calvac Paving can help service your construction job or to obtain a quote for services, please call us at 408-225-7700.